Re: [BLAST_SHIFTS] 10/03/02, morning shift

From: Mr. Shannon Krause (skrause@rocko.mit.edu)
Date: Fri Oct 04 2002 - 16:12:04 EDT


Aaron Joseph Maschinot wrote:
This magnet is LSIT2V. The upstream counterpart is
LSIT1V.

Shannon

> I was not able to perform tests with the downstream magnet current turned
> partially on but with opposite sign of normal running mode. CCR did not
> know which magnet I was asking about. They wanted to know its LS number
> (i.e. lattice steering number), which I did not know; it was not
> sufficient to say the "steering correction magnet located about a meter
> downstream from the target."
>
> Aaron

-- 
Shannon Krause
Operations Group Leader
MIT/Bates Linear Accelerator Center
PO Box 846, 21 Manning Road
Middleton, MA 01949-2846

617-253-9200 (front desk) 617-253-9206 (my office) skrause@rocko.mit.edu krause@mit.edu