[BLAST_SHIFTS] IMPORTANT - run plan

From: Tancredi Botto (tancredi@mitlns.mit.edu)
Date: Sun Dec 15 2002 - 14:35:24 EST


Sorry for this.
At midnight or just about we should switch the BLAST field OFF. Restart
the dissociator running. Have CCR adjust the ring tune as necessary.
Measure with ABS flow in the same conditions as previous shift.

Also, please do not forget that we always require to have the Wch on,
and to go through the checklist on pg 111.
-- tb
________________________________________________________________________________
Tancredi Botto, phone: +1-617-253-9204 mobile: +1-978-490-4124
research scientist MIT/Bates, 21 Manning Av Middleton MA, 01949
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^