[BLAST_SHIFTS] Shift summary 12/23/2003 A (0-4)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Tue Dec 23 2003 - 04:08:27 EST


Operators: baris kohlm nikolas

Data taking with fill-by-fill spin flipping (without automatic spin flipper).

A number of HV crates powercycles (three times in Dtunnel) were necessary.
A few spikes of the ligit invoked ABS alarm, but stable at 7.5E-8 otherwise
Increased LADS voltages by another 20 V starting with Run 4193
Good runs 4184-4186 4189 4191-4193. Runlist uptodate and crunching underway.

Collecting about 50-60 C per spin state per run. So far about 350C.
Probably switch on the spin flipper after three more good runs

MK