[BLAST_SHIFTS] Shift summary 06/06/2004 B (9-17)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Sun Jun 06 2004 - 17:24:10 EDT


Operator: karpiusp

No beam for 1st half of shift due to BLAST power supply tripping. Highest avail current was 6650 A. Spoke with Genya and Karen about this (note : I initially told Genya 6700 but it turns out this was not reliably achievable). So we took the best we could get and started taking data around 1300. Took runs 8189-8197 all crunching.



This archive was generated by hypermail 2.1.2 : Mon Feb 24 2014 - 14:07:31 EST