No beam for 1st half of shift due to BLAST power supply tripping. Highest avail current was 6650 A. Spoke with Genya and Karen about this (note : I initially told Genya 6700 but it turns out this was not reliably achievable). So we took the best we could get and started taking data around 1300. Took runs 8189-8197 all crunching.