Operator: seely

5:00 - plan was to take empty target data, but before DH left after his shift, he noticed some problems with the left wire chamber (box 30 not counting). He and AM struggeled mightily for five hours to try to fix the problem, but in the end figured out that some cards need to be changed. They will do this during the day today when the hall is opened.

CCR is also having trouble with the beam, and have given up for now since the hall will be open soon, and we have no need for the beam with the WC's in their current state.