[BLAST_SHIFTS] Shift summary 12/01/2004 A (1-9)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Wed Dec 01 2004 - 08:47:55 EST


Operator: clasie

ABS H running.

There were problems with stability in the ring and injecting to the maximum current. Often the current would decrease sharply and trip many detectors. Beam was given to CCR twice for tuning, but the instabilities continued.

There seems to be a problem with spud1, I can not ssh to it. This may also be the reason why the autocruncher is not working. Crunching for this shift was done manually.

6pole top and 6pole bottom pressures are wandering a little, but are staying below 10^-6 Torr.

The HV GUI was rebooted once.