Gain Matching continued this evening with the focus being on the right
sector. Again the target channel was 1500 ch above pedestal.
RTOF14 and 15 were not getting many events and were showing low coinc
rates on scalers. After checking the raw signals, 4516, MT, delay and
finally CFD outputs on scope the cause was found to be that the prompt out
for the top tubes were swapped. Things were righted and RTOF14 and 15
responded normally.
RUNS 2308-2315 Gain Matching of Right Side TOFS to pedestal + 1500
Most RTOFS seem to be within +/- 100ch of target channel.
These values still need to be recorded in an sql file.
Pete & Tavi
----------------------------------------------