[BLAST_SHIFTS] runplan 10-30

From: Tancredi Botto (tancredi@mitlns.mit.edu)
Date: Wed Oct 30 2002 - 00:09:18 EST


Night shift should take retime data for the following HV settings

_ commis.sql (presently loaded)
_ tof_1300.sql

I do not understand why there is absolutely no difference between runs
2377 and 2379 of this morning so something could have gone bad last night ?
All cables are now back to their orignal place, the only two bad cables
fixed.
 
The goal is also to understand why with tof_1300.sql some channels are
both smaller and bigger than the retime channel (+- 2-3 ns). This should
definitely not happen with the voltages of this summer so we should
check those first.

Adjust delay for tof_1300.sql. Then move on to tof_1500.sql. If there is
an access in the morning, we should definitely check again tof_1300.sql
and do some work on the odd channels in tof_1500.sql

Tot morgen
-- t
________________________________________________________________________________
Tancredi Botto, phone: +1-617-253-9204 mobile: +1-978-490-4124
research scientist MIT/Bates, 21 Manning Av Middleton MA, 01949
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^



This archive was generated by hypermail 2.1.2 : Mon Feb 24 2014 - 14:07:28 EST