[BLAST_SHIFTS] Shift summary

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Fri Jul 18 2003 - 23:45:05 EDT


Operators: baris degrush ----

No problems occured during data taking for the entire shift except for a minor transmitter problem. Coda, the hv control, compton never died once. This probably means there will be twice as many problems for the midnight shift.

Towards the begining of the shift the magnets were cycled to observe the affects it had on beam tune/position and SFT resonances. This required a retune of beam and resetting of current in the sft magnet.

Check updated runlist for runs.

All runs have either been crunched or are crunching.