[BLAST_SHIFTS] Shift summary 08/18/2003 A (0-4)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Mon Aug 18 2003 - 08:01:04 EDT


Operators: karpiusp seely ----

Took empty target data for most of shift. Crunched runs 2061-2085 for lr and charge.C, and all but 2081, 2084, 2085 for flrn

CCR had several crowbars and data taking stopped 3 times for about 30 min, during which the WC's were turned off.

Noted only slight change in WC signal to noise over course of shift - worst case being ~2:1 BQM's also remained stable.

Noted one jump in Ligit from 6E-9 to 1.5E-8, no explanation for this. Ligit eventually dropped back to 6E-9 Torr.

R24 and L6 tripped every now and then throughout the shift but rarely at significant frequency.
                                                PK



This archive was generated by hypermail 2.1.2 : Mon Feb 24 2014 - 14:07:29 EST