[BLAST_SHIFTS] Shift summary 12/15/2003 D (12-16)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Tue Dec 16 2003 - 03:42:01 EST


Operators: degrush nikolas ----

Continued Pol H2 60 sccm data injecting at 105 mA cell temp 100.

Runs taken:3997-4001

No asymmetry to report since all the runs taken today are still crunching.

A couple of times a sharp spike in ligit was seen followed by periodic oscillations in pressure that decreased in amplitude with freq of 0.1 hz. this would last for ~5 min. CCr could point to any thing out of the ordinary.
 

WC L21 tripped for 10 min and then stopped.

The following LADS channels trip everytime the slits are moved out before a new fill. They register a current trip (ST=20).

LADS channels Crate1

Slot.channel= 9.1 , 11.9-11.11, 12.0, 12.1 12.3, 12.6, 12.7, 12.9, 12.10, 12.11
13.3, 13.5, 13.6, 13.7