[BLAST_SHIFTS] Shift summary 07/04/2004 B (9-17)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Sun Jul 04 2004 - 16:56:37 EDT


Operator: baris

Shift started w/ polarized D2 data taking. Micheal called and informed about the nozzle regeneration which was initiated later by Ernie and Genya. Switched to unpol H2 before run 8555. Opened a new runlist "Runlist-H2.2" for crunch(ing)ed Hydrogen runs.
Runs:
ABS D2:8553-8554
Unpol H2:8555-8558

Baris