Operator: ajmasch
took more polarized deuterium runs.  shift started off smoothly.  somewhere in the middle, things went to hell for a bit; ccr had to re-phase a little, the roc's had to be hard-rebooted, and the compton got some broken pipes.  anyway, i think all is well now.
programs seem to be taking a very long time to open and close.  the elog's second screen (detector.tcl) takes around 5-10 minutes to close.  don't know why.
good runs:
  9125-9132 9138-9139