Hi,
Plan for the immediate future.
- Finish current run (empty target)
- Give beam to Jan for his studies on empty target
- switch off holding field, open V14, cycle holding field magnets
- run unpolarised D2 until ~01:00 Wednesday
- turn off cryo-pumps, switch back to running empty at 01:00 Wednesday
- open hall at 08:00 Wednesday morning to fill snakes and install
nozzle
- start running unpolarised D2 as soon as beam is available again
Cheers,
Douglas