[BLAST_SHIFTS] Shift summary 03/22/2005 B (9-17)

From: Electronic Log Book (elog@blast05.lns.mit.edu)
Date: Tue Mar 22 2005 - 17:02:22 EST


Operator: wangxu

Hi,
        Trabsmitter 6 is down so we had time to fill Snake. Karen also did some work for neutron wall. At 3:45 pm, beam was back. We start to take some data with a ABS target. However HV crate 2 kept on tripping. Now HV crate 2 is quiet.



This archive was generated by hypermail 2.1.2 : Mon Feb 24 2014 - 14:07:32 EST