Re:

From: Karen Dow (kdow@mit.edu)
Date: Tue Sep 10 2002 - 11:32:26 EDT


John,

        Kelsey thinks he could make a jig to repair joints in place, but he'd
want to pull the Cerenkov-4TOF group to work on designing and testing
the jig. Beam is unavailable all next week while the ABS installation
is finished, so that would be a time to pull the whole thing. We
probably should have a jig to do in-situ repair, for possible future
problems, even though we could fix this one more easily.
        
        You should check with Kelsey in case I've misunderstood what he said.
The hall will be open days for Thursday and Friday this week for some
ABS work. But beam will be available nights and this weekend.

                                        Karen